3000 SQUARE FOOT AMAZON SORTATION FACILITY

BUSINESS: DISTRIBUTION
CATEGORY: WAREHOUSE DISTRIBUTION
LOCATION: OKLAHOMA CITY, OK
SQUARE FEET: 300K
PARTNERS: INDUSTRIAL DEVELOPERS OF OKLAHOMA, FLEMING CONSTRUCTIONS GROUP
FSE COMPLETES STEELWORK ON AMAZON SORTATION CENTER IN JUST 90 DAYS

In partnership with Industrial Developers of Oklahoma and the Fleming Construction Group, on behalf of multi-national eCommerce and technology behemoth, Amazon, Fleming Steel Erectors was commissioned to erect the structural steel and roof for Amazon’s new 300K sq. ft. Oklahoma City sortation center.

FSE’s contracted scope included integrating the structural steel and roof system with full height perimeter tilt-wall panels. Consisting of 2,300 linear feet of connection and roof transitions, this aspect of the project was completed in just 90 days. The entire project from ground-breaking to certificate of completion was finished in eight months.

PROJECT SCOPE

  • Butler Landmark Structural System
  • 32’ Clear Height
  • 16K Sq. Ft. of Office Space
  • R30 Roof Insulation
  • Full Height Concrete Tilt Wall with 2,300 Linear Feet of Connections Between Concrete Wall Panels and Structural Steel
  • (3,750) MR24 Roof Sheets, (2,500) Long Bay Truss Purlins, (480) Frame Member Beams, (210) Interior Columns, (9) Bays of Roof Bracing

RESULTS

  • ‘Weathered In’ (Structural Steel and Roof System Erected) in 90 Days
  • Entire Project Built in Eight Months from Ground Breaking to Completion
  • 17,000 Man-Hours with Zero Safety Incidents
  • ACG and ABC Industrial Project of the Year Award Winner

“The Amazon sortation center was perhaps the most important development project we had tackled to date, with a demanding schedule requiring that the building be functional and ready to deliver packages for the holidays. Failure wasn’t an option, and the team at FSE didn’t let us down. Realizing that the steel package aspect of the job was critical to overall project success, FSE gave us a weathered-in shell a week before the initially scheduled deadline – an accomplishment that was invaluable in helping us meet our timeline obligations. We greatly appreciated the effort and professionalism required to accomplish this and to do it safely.”

– Matt Klimisch, Founding Partner, IDO